A46 Warwick bypass resurfacing and contraflow working – 26th July to 12th September
Due to the poor condition of the carriageway a full depth reconstruction is required – this should reduce the need for further repairs in the coming years
This requires the removal, to the sub-core, circa 400mm of excavation for a duration of about 4kms of the northbound carriageway
July, August and early September were seen as the best months to complete this as road traffic would be at its lowest
This also avoids the busy education periods (with the expectation) that the carriageway can be restored pre the school autumn term returning
Restrictions during contraflow working
A46 (northbound) services will be closed
No Exit or Entry (northbound side) slip roads closed for duration of works at Stanks also known as Budbrooke
No Exit (northbound side) slip road will be closed at Leek Wootton
A46 (southbound) services will be closed
No access across the coning from the northbound side into / out of the services for northbound traffic